The CHRO closeout checklist
Substantial completion starts a 45-day clock. Here's what has to reach CHRO before it runs out — and a calculator so you know your exact date.
What to submit (print this)
-
Subcontractor payment documentationProof of every payment to every subcontractor and supplier — including dates, so prompt-payment compliance (15 days) is demonstrable.
-
Executed lien waiversFrom subcontractors and suppliers, collected as payments finalize — not scrambled for in week six.
-
Outstanding subcontract notificationsAny subcontract award notifications that weren't already sent to CHRO during the project.
-
Final SBE/MBE spending summaryActual certified-firm spending against the project's Spending Allocation Goals.
Based on Connecticut statutes and CHRO guidance as of July 2026. Verify current requirements with official sources; this is not legal advice.